Evidence Checklists

This appendix turns the Project Information Model standard into evidence tests. A sponsor should upload evidence to Atlas or the data room before marking a section complete.

EvidenceRequiredReviewer Test
Project name, sponsor, operator, and frameworkYesAre core identities complete and consistent across documents?
GIS boundary and site mapYesCan the asset be located and mapped?
Site rightsYesDoes the sponsor have lawful access or control?
Version registerYesIs the Project Information Model status clear?
EvidenceRequiredReviewer Test
Demand evidenceYesAre users, customers, or buyers identified?
Pricing evidenceYesAre prices sourced and current?
Offtake or customer recordsWhen relevantIs the commitment type labeled accurately?
Utilization rampYesDoes the ramp match implementation and market evidence?
EvidenceRequiredReviewer Test
Design basisYesDoes the design solve the stated problem?
Capacity calculationYesDoes capacity match demand and revenue assumptions?
Vendor quotes or cost basisYesAre costs traceable?
WBS and scheduleYesAre dependencies and acceptance criteria clear?
EvidenceRequiredReviewer Test
Stakeholder agreementsYesAre roles enforceable or documented?
Community participation evidenceYesIs local participation economic and real?
Stewardship designYesAre residual economics and ecological purpose defined?
Grievance mechanismWhen stakeholders are affectedIs there a usable escalation path?
EvidenceRequiredReviewer Test
Financial modelYesAre assumptions driver-based and sourced?
Sensitivity analysisYesAre downside cases meaningful?
Risk registerYesDoes each risk have owner, mitigation, indicator, and trigger?
Compliance trackerYesAre approvals mapped and status evidenced?